White Square Jikia

07.04.2026

White Square Jikia

07.04.2026

Update on the construction progress:

ინფორმაციის შენახვა

o Main door and window installation works have been completed, with only the installation of front façade vitrages remaining.
o Electrical wiring works in apartments are currently underway on the 18th floor.
o Water supply, drainage, and gas piping works have been completed up to the 18th floor.
o Internal wall plastering in apartments is in progress on the 19th floor.
o Floor screeding has been completed up to the 17th floor.
o Installation of balcony railings is underway on the 15th floor.
o Corridor tiling has been completed up to the 16th floor.
o Balcony tiling has been completed up to the 15th floor.
o Staircase tiling has been completed up to the 15th/16th floors.
o Installation of one elevator has been completed and is currently undergoing operational inspection.
o Installation works for the second elevator are in progress.
o Façade works have been completed up to the 17th floor.
o Installation of the main entrance door has been completed up to the 16th floor.